The Bayelsa State Commissioner for Information, Strategy and Orientation, Ebiuwou Koku- Obiyai, has assured that the 60 Mega Watt Gas Turbine, will soon come alive adding that the President Bola TInubu will be on ground to commission it.
Speaking on Tuesday in Yenagoa to Federated Correspondent Chapel members of NUJ after they went to inspect the Gas Turbine, she admitted that she can’t actually say when the turbine will be coming up.
Obiyai called on Bayelsans to keep on supporting the Prosperity Government adding that it is not good for people to stay at home and criticize.
“You see, the time for the gas turbine to come up is the problem now because we don’t want to give time again. Over the months, we’ve been giving time. This time now we want everything to be set.
” And we are believing that the president of this nation will come and commission it. So there are a lot of processes to tie that up. So I want Bayelsans to continue to support the government.
“Because you have gone and you have seen it with your eyes. That’s why I always say, it’s not so good to remain at home and criticize. You go and see what your government is doing.
“The government is doing so much, we have invested so much.
And I believe that Bayelsans will benefit from it, all of us. So let us calm down, continue to believe. And I know in no distance time, the light will be up.
Conducting journalists round the facility at Elebele Community earlier, the site manager, Engineer Steve Bubagha disclosed that he couldn’t give the exact day that they gas turbine will come alive adding that the gas turbine is almost ready.
Maintaining that nobody will reveal when the gas turbine will be coming up but soonest, he said that almost everything is ready stating that they were just checking the nuts and making sure that everything is alright.
He said:”Nobody is going to tell you when the turbine is coming up. Assessing it, you should be able to deduce. If you have visited here before, and you are visiting here again, you should be able to know.
“What we are doing now is, we are checking what we’ve done. We are checking to see that we have not started testing wrongly. I don’t want to use the word commissioning. But all the bolts, all the things we’ve done, we are going back to them and cross-checking.That’s what we are doing now.
“The turbine is a very sensitive issue and so, when we are addressing the public, we are also very, very careful about what we say.
You’ve been here before, you’ve seen it, you should be able to deduce and say, yes, we have achieved it.
“However, by the mercies of God, a day is coming when we are going to on the light. When? I can’t say, I can’t reveal that to you. It’s only the MD that will be able to reveal that to you.
“For now, it’s Yenegoa metropolis that will be covered. We’ve said that often and often. The wiring is almost completed but I will not be able to tell you anything about metering.
“We are working with Jampur group but they are not the manufacturers. The manufacturers are actually General Electronics.”
He said that the gas turbine will serve Yenagoa only from Igbogene to Swali adding:” that is the preparation we have done for the network.”
The essence of the initiative he said is for Bayelsans to enjoy power. “The essence of having this unit is to boast the economy. “When there is steady power supply, the economy will boom.” He narrated.
Recall that citizens of Yenagoa had been waiting for the gas turbine to come up from December last year to this February and now to very soon thereby dashing their high hope.
Of course, Bayelsans behave been lamenting because almost everything has been at a standstill as the PHED is not giving light while the gas turbine that Bayelsans are hoping on is yet to be powered.